Demonstration plant WST in Ronneby

Ronneby Miljö & Teknik AB is a municipal company that is wholly owned by the municipality of Ronneby. Their goal is to combine environmental responsibility with economic efficiency. They are currently preparing the installation of a Wet Steam Turbine for electricity production on the existing district heating plant.

 

Sörbyverket

Ronneby Miljö & Teknik AB is a municipal company that is wholly-owned by the municipality of Ronneby. They manage power, heat, water, sewage, sanitation, fiber optic networks and broadband. Sörbyverket, the regional district heating plant, is operated by the subsidiary company, Ronneby Miljöteknik Energi AB. They are currently building a Wet Steam Turbine (WST). Through the possibility of producing renewable electricity in Sörbyverket, the corporation will be self-sufficient in electricity. 

Ronneby Miljö & Teknik have chosen to install a WST since the boiler of Sörbyverket has the opportunity of steam production. The existing system in Ronneby is currently being adapted to enable a connection of the WST.

The changes that needs to be done are mainly modification of the boiler circulation and existing steam dome. Safety equipment, dryout protection, etc. needs to be supplemented and upgraded. In addition, the boiler needs to be supplemented with feed water system consisting of feed water, feed water pump and safety valves. In total, Sörbyverket will use 65 % of the generated power, selling the remaining electricity within the corporation group. 

The WST will be delivered to Sörbyverket in the beginning of October 2016. 

 

WST

A Wet Steam Turbine (WST) is relatively easy to implement - the upgrade takes place in the boiler water circuit without extensive reconstruction of the boiler. Compared to conventional steam turbines, WST can operate at lower pressure and lower temperature. 
WST is a more robust and a less high-efficiency turbine and which 
unlike conventional turbines, even can handle some water particles.

Download the fact sheet

WST Plant data

EFFECT

600 kW of electricity

OPERATING HOURS/YEAR

Approximately 5200 hours

ELECTRICITY

Approximately 2700 MWh / year

INVESTMENT COST

Approximately 15.2 million

THE ESTIMATED PAYBACK

Approximately 5-6 years

RAW MATERIAL

Wood chips, forest residues, bark, etc.

MOISTURE IN RAW MATERIAL

35-50%

MODEL

M+M Mini-Turbine

 

 

 

For more information,
please contact

 

Karoline

Karoline Alvånger

Project Manager pro term

 

Tel: 0709-21 60 52

E-post

 

Plants for small-scale Combined Heat and Power production are built in Southeast Sweden for demonstration of techniques. 
 

Project runs from July 2014–December 2019

 

Partners 

Emå dairy and Ronneby Miljö & Teknik AB

with support from EU financial instrument Life+ and Swedish Energy Agency


The WST will open for study visits in autumn of 2016. More info coming. 


Back to project information >>

Demonstration plant WST >>

Demonstration plant gasifier >>


Links

 

  

  Information in Swedish

 

 

 

 

WST delivery in October

2016-08-26 

 

Sörbyverket will soon be ready for electricity production.  Most preparations are made for the delivery of the WST in October.

 

Investment of ORC in BräkneHoby

2016-06-29

Ronneby Miljö & Teknik AB is planning for an Organic Rankine Cycle in a thermal power station in BräkneHoby. The procurement of the ORC is currently in process. 

 

Exhibition on Ronneby Energy and Environmental Fair

2016-04-27 

Project leader Daniella Johansson talked about Small Scale CHP Life+ and local demonstration plant on Ronneby Energy and Environmental Fair.